Playground / Nature and environment
Practise screening a project under India’s EIA Notification, 2006: find its Schedule item, test its size, apply the General Condition for nearby protected and polluted areas, and see whether it is Category A, B1 or B2, who appraises it and which clearance stages follow.
Learning tool. This tool simplifies the official method and uses sample or default data. Do not use its results for business decisions, regulatory filings, assurance, investment or legal compliance. Framework and standard names belong to their owners; Sigma Earth is not affiliated with or endorsed by them. Terms of use
New here? Sample numbers are already filled in, so you can see a full result straight away. Change any number and the result updates by itself; nothing can break. You only need an account to save your work.
“Not listed” means no prior environmental clearance under this notification. It does not mean no approvals: forest, wildlife, coastal and pollution board permissions are separate.
A sample project is filled in: a 60 MW hydroelectric project 7 km from a wildlife sanctuary. Work through the four steps and change anything. The result updates as you type.
India’s Environment Impact Assessment (EIA) Notification, 2006 (S.O. 1533(E), 14 September 2006) was issued by the Ministry of Environment, Forest and Climate Change (MoEFCC) under the Environment (Protection) Act, 1986. Every project or activity listed in its Schedule needs prior environmental clearance before any construction or land preparation starts (only securing the land is allowed).
The Schedule sorts projects into Category A, appraised by the MoEFCC on the advice of an Expert Appraisal Committee (EAC), and Category B, appraised by the State Environment Impact Assessment Authority (SEIAA) on the advice of a State Expert Appraisal Committee (SEAC). At screening, Category B is split into B1 (needs an EIA report and usually a public hearing) and B2 (appraised on the application alone). The General Condition moves a Category B project to central level as Category A if it lies within 5 km (10 km for some items) of a protected area, a critically polluted area, an eco-sensitive area or an inter-state or international boundary.
Recent changes: the notification has been amended well over a hundred times. On 29 January 2025 (S.O. 523(E)) item 8 for buildings and townships was rewritten, and it says the General Condition does not apply to it. In July 2026 (S.O. 3862(E), as reported) standing state bodies were created to step in when an SEIAA or SEAC is not functioning. On 18 November 2026 (S.O. 6278(E), as reported) non-coal mining leases of up to 500 ha (previously 250 ha) moved to the states. A draft replacement notification published in 2020 was never finalised, so the 2006 notification remains in force.
This tool covers twelve common project types: mining (major minerals and coal), hydroelectric and irrigation projects, thermal power, cement, highways, airports, hazardous and municipal waste facilities, buildings and townships, and solar or wind as a not-listed example. It leaves out mining of minor minerals (whose district-level route is before the courts), pump storage projects (which can be B2 whatever their capacity under a 2023 note), industrial estates, ports, chemical and other industries, the expansion routes of paragraph 7(ii) (for an expansion the expert committee decides the studies; the tool assumes the full route), and the Coastal Regulation Zone, forest and wildlife approvals.
Each test uses the Schedule to the EIA Notification, 2006 as amended. Worked numbers use the sample project (a 60 MW hydroelectric project 7 km from a wildlife sanctuary) and two others.
| Test | Rule | Worked example | Source |
|---|---|---|---|
| 1. Is it listed? | Match the project to one item of the Schedule. If no item covers it, or it is below the lowest threshold, no prior environmental clearance is needed under this notification. | A 20 MW hydroelectric project is below 25 MW, so it is not listed; a solar park is not in the Schedule at all. | EIA Notification 2006, paragraph 2 and Schedule |
| 2. Size test | Compare the size with the item’s Category A (column 3) and Category B (column 4) thresholds. Examples: hydroelectric A ≥ 100 MW, B 25 to below 100 MW; coal-based thermal A ≥ 500 MW, B above 5 to below 500 MW; non-coal mining A above 500 ha, B up to 500 ha; buildings 8(a) 20,000 to below 1,50,000 sq m; townships 8(b) ≥ 50 ha and/or ≥ 1,50,000 sq m. Expanding only an airport’s terminal buildings inside its existing area is appraised like 8(a) from above 20,000 up to 1,50,000 sq m (note (ii), 2022). Pump storage projects meeting three criteria are B2 whatever their size (note (iv), 2023; not modelled). | Sample: 60 MW is from 25 up to below 100 MW, so Category B by size. | Schedule items 1(a), 1(c), 1(d), 3(b), 7(a), 7(d), 7(f), 7(i), 8 |
| 3. General Condition | Where the Conditions column says it applies (this tool does not apply it to airports, whose column is silent, and the Schedule says it does not apply to item 8): a Category B project in whole or in part within 5 km of a protected area, critically polluted area, eco-sensitive area, or inter-state or international boundary is appraised centrally as Category A. River valley, thermal power, industrial estates and hazardous waste facilities use 10 km. The inter-state distance may be reduced by agreement between the states. A reservoir lying in two states crosses the boundary, so it is at 0 km. | Sample: the sanctuary is 7 km away, within the 10 km for river valley projects, so it becomes Category A. At 12 km it would stay Category B. | Schedule, General Condition (as substituted 2014) |
| 4. B1 or B2 | The Schedule’s own notes (for example medium irrigation is B2, major irrigation and townships are B1), Appendix V paragraph 3 (item 8(a) needs no EIA report) and the 2013 guidelines (for example a grinding unit moving at least 90% by rail is B2). Every other Category B project is B1. The SEAC may move a B2 project up to B1. | A 48,000 sq m building is 8(a), B2: Form 1, Form 1A and a conceptual plan, no EIA report. | MoEF OM J-13012/12/2013-IA-II(I), 24 Dec 2013; Appendix V |
| 5. Who appraises | Category A: MoEFCC on the EAC’s advice. Category B: SEIAA on the SEAC’s advice, except river valley projects in more than one state, irrigation with inter-state issues and declared defence or strategic projects, which are appraised centrally as Category B. | Sample (Category A): MoEFCC, EAC for river valley and hydroelectric projects. | Paragraphs 4(ii), 4(iii), 4(iiia); Schedule notes to item 1(c) |
| 6. Stages | Screening (Category B only), scoping (terms of reference, for A and B1), public consultation (A and B1, except buildings and townships, approved industrial estates, highway expansions with no new land, highways in border states, modernisation of irrigation projects, defence projects), appraisal within 60 days, decision within 45 days of the recommendation. For an expansion or modernisation the committee decides the studies needed (paragraph 7(ii)(a)); the tool assumes the full route. | Sample: no screening; terms of reference; public hearing by the State Pollution Control Board within 45 days of the request; appraisal; decision. | Paragraphs 7 and 8 |
| 7. Validity | River valley projects 13 years; mining the project life in the mining plan up to 30 years, counted from the execution of the mining lease; others 10 years; townships 10 years for the developer’s own activities. | Sample: 13 years to start operations. | Paragraph 9 (as substituted 2022) |
Screen five proposals of a fictional infrastructure developer: work out a building’s built-up area and a plant’s capacity, apply the thresholds and the General Condition, decide each category and who appraises it, and spot which need a public hearing.
Checked against the sources below in November 2026. Rules change: always use the official text for real work.
Category A projects have the larger potential impacts and are appraised by the central government: the MoEFCC decides on the advice of an Expert Appraisal Committee. Category B projects are appraised by the state: the State Environment Impact Assessment Authority (SEIAA) decides on the advice of the State Expert Appraisal Committee (SEAC). The Schedule of the EIA Notification, 2006 sets the threshold for each type of project.
It is a rule in the Schedule that moves a Category B project to central level as Category A if any part of it is within 5 km of a protected area under the Wild Life (Protection) Act, a critically polluted area identified by the CPCB, a notified eco-sensitive area, or an inter-state or international boundary. River valley projects, thermal power plants, industrial estates and hazardous waste facilities use 10 km. It applies only to items whose Conditions column says so; since January 2025 the Schedule says it does not apply to buildings and townships.
Both are Category B, appraised by the state. A B1 project needs terms of reference, an EIA report and normally a public hearing. A B2 project is appraised on the application (Form 1 with a pre-feasibility report, or Form 1, Form 1A and a conceptual plan for buildings) without an EIA report or public hearing. The State Expert Appraisal Committee decides at screening, using the Schedule notes and the Ministry’s guidelines.
Solar photovoltaic parks and wind farms are not listed in the Schedule of the EIA Notification, 2006, so they need no prior environmental clearance under it. They may still need other approvals, for example forest clearance if they use forest land, wildlife approval near protected areas, and state rules.
No. Paragraph 2 says no construction work or preparation of land may start before prior environmental clearance, except securing the land. Starting earlier is treated as a violation.
Yes. Item 8 for buildings and townships was rewritten on 29 January 2025; standing state bodies to keep appraisals running were added in July 2026; and on 18 November 2026 non-coal mining leases up to 500 ha (previously 250 ha) moved to the states. A draft notification of September 2025 to exempt some cement grinding units was still a draft when this tool was checked. Always check the latest gazette before relying on a threshold.
No. You need a free account only to save results or take the graded case.
No. The Playground is for learning only. It simplifies the official methods and uses sample data, so its results must not be used for business decisions, regulatory filings, assurance or investment. Use the official standard and qualified advice for real work.